A full kitchen remodel around Milton and Alpharetta usually runs four to eight weeks on site, and the calendar starts well before the first cabinet comes out.
The Short Version: How Long Does a Kitchen Remodel Take?
For a full kitchen remodel with a new layout, new cabinets, countertops and lighting, plan on four to eight weeks of work on site once the materials have arrived. A refresh that keeps the layout is quicker. If you're opening the kitchen to the next room, plan toward the longer end of that range.
So how long does a kitchen remodel take from the first call to a finished room? Longer than the on-site weeks, because decisions and orders come first. You'll get a realistic schedule before work starts, not a hopeful one.
Why the Calendar Starts Before Demolition
The on-site weeks are counted from the day the materials are in hand. Everything before that, the choices and the orders, is what really sets your start date.
Layout changes add a step. Moving walls, plumbing or electrical in Fulton, Gwinnett or Cherokee County typically needs a permit. In Alpharetta, interior remodel plans are reviewed before that permit is issued. That review runs on the city's calendar, so it goes into the plan early.
That matters here. Many of the homes we work on around Milton and Alpharetta, from Crabapple to Windward, have kitchens closed off from the family room. Opening them up is exactly the kind of change that needs plans.
What You'll Need Decided Before Work Starts
These choices drive the order dates, so they come first. Each one settled early is one less pause once the walls are open.
- Whether any walls, plumbing or gas lines move
- The cabinet line and the layout
- The countertop material
- Appliance models, since the cabinet openings depend on them
- The sink, faucet and lighting plan
- The backsplash tile
- Where your temporary kitchen corner goes
The Process, Phase by Phase
- Walkthrough and a written quote. We walk your kitchen with you, take measurements, and check the plumbing and electrical. We talk through how you cook and what frustrates you about the room today. Then you get one written quote you can read line by line, before anything is scheduled. Photos of kitchens you like and a list of what bugs you about yours make this step faster.
- Selections and material orders. Cabinets, countertops, fixtures and lighting are chosen together, then ordered. Whatever has the longest lead time, often the cabinets, sets the start date. You'll know that date before demolition is booked, so nothing sits half-torn-out while a box is on a truck.
- Plans and permit, when the layout changes. If walls, plumbing or electrical move, the job typically needs a permit. Alpharetta wants a scaled floor plan and a mechanicals plan, reviewed before the permit is issued. The permit is arranged before work starts, and the inspections are built into the schedule.
- Protection and demolition. The work area is sealed off from the rest of the house, and a temporary kitchen corner goes in. The rest of the house stays protected and usable. Then the old cabinets, counters and flooring come out. This is when anything hidden behind a wall shows up, and any change is priced and agreed with you before it's done.
- Rough-in and inspection. Framing, plumbing, electrical and lighting runs go in while the walls are open. Where a permit is open, the rough inspection happens before the walls close. Alpharetta's guide lists rough and framing, insulation and final inspections, so each one has a slot in the plan. Inspections are booked into the schedule rather than requested at the last minute.
- Cabinets, countertops and finish. Drywall goes up, then the cabinets. Countertops are templated once the cabinets are set, then cut and installed. The backsplash, fixtures, appliances and lighting come last, followed by a final walkthrough. You get a finished kitchen, not a punch list.
When to Talk to Us About Your Schedule
If the kitchen has to be done by a certain date, start the conversation early. A holiday, a move-in or a family visit works backward from decisions and orders, not from demolition day.
If the room is simply too small to fix inside its walls, a home addition is the other conversation to have. Either way, the free walkthrough is where the real schedule starts. We're an owner-run remodeler based in Milton, working across North Atlanta since 2014. Get Started and tell us what you have in mind. Send the form during business hours and you'll hear back the same day.
Frequently Asked Questions
Can we stay in the house during a kitchen remodel?
Almost everyone does. We set up a temporary kitchen corner, seal off the work area from the rest of the home, and tidy up at the end of every day.
Is a kitchen refresh faster than a full remodel?
Yes. A refresh that keeps the layout skips moving walls, plumbing or gas lines, so it runs quicker than a full kitchen. Your quote spells out which one you're getting.
What usually makes a kitchen schedule slip?
Late selections, a back-ordered item, or something found behind a wall. Locking choices in before demolition handles the first two. The third gets priced and agreed with you before any change is made.
Which city issues a kitchen permit if my address says Alpharetta?
The city your parcel sits in, which is not always the one on your mail. Many Milton homes carry an Alpharetta or Roswell address. Our guide to basement permits in Milton and Alpharetta explains how to check before plans are drawn.